- Project Type:GeoQ third party CQA and Electrical Leak Detection
- Date:April, 2021
GeoQ were engaged by Origin Energy to undertake, Level 1 CQA supervision, electrical leak detection (ASTM D7953- 20) Arch testing exposed geomembrane and also water covered Di-pole testing (ASTM D7007- 16). GeoQ also successfully completed commissioning process of the pond.
Project Facts:
- 200,000m2 of 1.5mm HDPE.
- 90,000m2 of Geonet.
- 45,000m2 of Bituminous Liner
- Continuous 3 man GeoQ team dedicated to CQA and electrical leak detection activities.